Tunbridge Wells Borough Council has approved £23.5m to rebuild Palm Court at Royal Victoria Place. Work could start in January 2028 and finish in 2029.

Tunbridge Wells Borough Council has approved a further £23.5 million to rebuild Palm Court, the central atrium of Royal Victoria Place. Full Council backed the plan at an extraordinary meeting on Wednesday 11 November.

The council owns the shopping centre. It announced the decision on 13 November and said the building work could start in January 2028 (Tunbridge Wells Borough Council).

Overview

  • Decision: Full Council approved the Palm Court scheme and its funding on 11 November 2026.
  • Cost: an extra £23.5 million, on top of £3.3 million for design approved in July 2025.
  • Start: building work could begin in January 2028, with Palm Court finished between April and June 2029.
  • The centre stays open: the design team says one key Palm Court tenant has renewed its lease and plans to trade through the works.
  • Still to decide: the cinema and restaurant phase at Ely Court goes to its own Full Council vote, planned for April 2027.

What the council approved

The council has said Palm Court “has changed very little” since the centre opened in the 1980s, and that its roof is reaching the end of its life (Tunbridge Wells Borough Council). The scheme already has planning permission. The council says it will bring:

  • a new energy-efficient roof “inspired by Victorian glass palm houses”
  • new leisure space in the former basement food court
  • a brighter atrium, with new lighting, flooring and finishes
  • new toilets, including accessible toilets and a baby changing area
  • more space for existing shops, and room to attract new brands

No leisure operator has been named. The council says the design responds to three rounds of public engagement, including a borough-wide online survey of 2,860 people.

Cllr Justine Rutland is the Cabinet Member for Economic Development. She also chairs the cross-party Investment Advisory Panel. She said: “Getting the Palm Court proposals approved by Full Council is fantastic news for Tunbridge Wells and a big step towards breathing new life into Royal Victoria Place.”

The money, and where it breaks even

The report to Full Council puts the total development cost at £25,403,459. That includes £4.47 million of contingency. The council would borrow £23,272,147, and its model assumes a single loan at 6 per cent.

On those figures, officers expect the council to finish £315,559 a year better off once the extra rent, parking income and business rates come in. Councillors on the finance advisory board asked in October to see where that surplus runs out. The updated table answers it:

  • at the current cost, the surplus disappears at an interest rate of 7.5 per cent, where it becomes a loss of £1,597 a year
  • if the cost rises by £2 million, it turns to a loss at 7 per cent
  • at 5.75 per cent and the current cost, the surplus rises to £366,827
Bar chart of the council's modelled yearly surplus from the Palm Court scheme at a total cost of £25,403,459, by borrowing rate: £366,827 at 5.75%, £315,559 at 6%, £263,787 at 6.25%, £211,541 at 6.5%, £158,852 at 6.75%, £105,748 at 7%, £52,256 at 7.25%, and a loss of £1,597 at 7.5%.
The council's own sensitivity table at the current cost estimate. Chart by Tunbridge Wells Today.
Share this chartFacebookWhatsAppX

The report says the council does not have to borrow it all at that rate. The Public Works Loan Board has guaranteed lending. The council can also borrow internally from spare working capital at a notional rate of around 4 per cent, and its treasury advisers found a possible surplus of over £20 million. No money will be borrowed until a contractor is appointed.

The same vote approved £400,000 to start procuring a builder for the whole scheme, including Ely Court. It also set up a reserve for the development and confirmed that Palm Court can go ahead alone if Ely Court is delayed.

What happens next

The report’s timetable:

Step Date
Ely Court planning application decided February 2027
Full Council vote on Ely Court and the full scheme April 2027
Contractor appointed July to September 2027
Building work starts January to March 2028
Palm Court finished April to June 2029
Ely Court finished, if approved October to December 2029

Plans for housing on Market Square have been dropped from the scheme for now. The report says they were not viable in the current housing market.

What it means for you

  • Nothing changes yet. The centre trades as normal through Christmas and 2027. The design team’s executive summary says the start was moved from December 2027 into January 2028 to allow for undisturbed Christmas trading.
  • The borrowing is the council’s. If the centre earns less than forecast or interest rates rise, the gap falls on the council’s budget, not directly on your council tax bill.
  • Ely Court is still open. The cinema and restaurant phase needs planning permission and a separate vote. We covered the costs and the listing row in our report before the vote.

Sources: Tunbridge Wells Borough Council, “Royal Victoria Place transformation gathers momentum”, 13 November 2026; Royal Victoria Place (RVP) Development: Palm Court, report to Full Council, 11 November 2026, on the meeting page.