A Puffin crossing will replace the Mascalls Court Road zebras in Paddock Wood. First come lane closures and a water cut at Badsell Road, 17 to 19 November.
A new signal-controlled Puffin crossing is planned for Mascalls Court Road in Paddock Wood. It will sit by the skateboard park and replace the zebra crossings there. Paddock Wood Town Council has given land so the footway can be widened.
The plan is in the November update from Breheny Civil Engineering, which is rebuilding the Badsell Road and Maidstone Road junction for Kent County Council. (Badsell Road project update, November 2026)
The same update confirms that Badsell Road has reopened. It was shut from 19 October, and the contractor says the closure was “completed as planned”. The next disruption is close behind: a lane closure and an overnight water cut on 17 to 19 November.
Overview
- Badsell Road is open again after the October closure.
- 17 to 19 November: one lane shut, with temporary traffic lights, on the approach to the Maidstone Road and Badsell Road junction.
- Overnight on Wednesday 18 November: South East Water connects a new main, and some homes will lose their water for a time.
- Mascalls Court Road: a Puffin crossing replaces the zebras. Clearance work is expected in the February 2027 half term and the main work in the Easter holidays, which is expected to need the road closed.
The lane closure and the water cut
South East Water is connecting a new water main in the grass verge on the west side of Maidstone Road, near the Badsell Road junction. The contractor’s notice sets out three days of work under the same single-lane closure and temporary signals:
| Day | Hours | Work |
|---|---|---|
| Tuesday 17 November | 9.30am to 3.30pm | Digging |
| Wednesday 18 November | about 11pm to 3am | The main connection |
| Thursday 19 November | 9.30am to 3.30pm | Reinstatement |
The overnight connection needs a temporary shutdown of the water supply. South East Water will contact the affected homes directly, the notice says. It does not say which streets. (Public Information Notice 07)
A wider path on Maidstone Road
Work to rebuild the eastern footway of Maidstone Road began at the start of November. It is expected to take about eight weeks. The result will be a wider shared path for walking and cycling, with tactile paving at the crossing points.
The contractor says it will help pupils of Leigh Academy Mascalls as well as residents and commuters. While a section is being dug up, people on foot are sent across to the western footway at temporary controlled crossings.
The Puffin crossing
The Mascalls Court Road changes were drawn up with Paddock Wood Town Council and Leigh Academy Mascalls. They include:
- a Puffin crossing by the skateboard park, replacing the existing zebra crossings
- a wider footway, on land the town council has made available
- a replacement hedgerow
The contractor says the changes should make the road easier to cross on foot and “help relieve traffic queues on Maidstone Road”. Vegetation clearance is timed for the February 2027 half term, before the main bird nesting season. The main construction is planned for the Easter holidays and “is expected to require a temporary closure of Mascalls Court Road”. The contractor says it will give details nearer the time. (Mascalls Court Road drawing)
Where the junction scheme has got to
The October closure let three jobs happen with the road shut:
- BT carried out utility diversion work near Mascalls Park
- UK Power Networks diverted its overhead lines on Badsell Road
- a short stretch of road was rebuilt at the Mascalls Park junction
Earthworks for the new line of Badsell Road are now about half done. The new road is being built beside the old one, so the existing road can stay open “wherever possible”. The scheme is meant to cope with traffic from around 1,000 new homes nearby, and is due to finish in late spring 2027. (Badsell Road Junction Improvement Scheme)
What it means for you
- Driving through on 17 to 19 November? Expect temporary lights and queues at the junction, by day on the Tuesday and Thursday and overnight on the Wednesday.
- Live near the junction? Fill a kettle and a few bottles before 11pm on 18 November if South East Water tells you your supply will be off.
- Walking to Mascalls? Use the western footway of Maidstone Road where the eastern one is fenced off, crossing at the temporary lights.
- Questions: the project team is on badsellroad@breheny.co.uk or 07976 367359, Monday to Friday, 9am to 5pm.